Construction Photos - February 2013































1 comment:

  1. February 2014
    The final pieces of the puzzle are being brought in and put together. Site work and City Improvements are moving along well. The interior corridors and elevator lobbies are pushing completion up the building. The unit finishes and furniture installation is almost complete and we are cleaning up rooms for the final Marriott punch walk. The meeting rooms and back of house spaces are nearly complete and the Hearth Room ceilings are going in. Terrazzo is being laid on the lobby floor along with the accent wood paneling. The pool deck paver system is being installed; planters are next on the list along with pool plastering and landscaping.